Bridge progress

Sunday 2nd September saw the completion of the concrete pour for the “nearside” pad stone having completed the offside one the previous Thursday

Both will be given a couple of weeks to cure before the brickwork goes on and then another 6 weeks after the brickwork before the steel.

Planned dates:
Brickwork weekend is 22nd September
Materials to site weekend is 13th October
Bridge deck assembly weekend is 10th November

Plus our regular sessions every Thursday weather permitting.

Come along and see or even join in. All welcome